3.2 MWpsolar farm
3.2 MWenergy storage
PermitOct 2026
Hybrid PV + BESS to RTB – Jeżów Sudecki
Building design of a hybrid installation: a 3.2 MWp solar farm with a 3.2 MW energy storage system in the Jeżów Sudecki municipality. The project has obtained its building permit.
Parameters
- Solar farm
- 3.2 MWp
- Energy storage – power
- 3.2 MW
- Installed capacity of the source
- 6.4 MW
- Connection capacity
- 3.2 MW
- Auxiliary consumption
- 0.1 MW
- Installation type
- hybrid PV + BESS
Milestones
- Update of grid connection conditions
- Environmental decision (25 May 2026)
- Contract for the building design and building permit
- Building permit application filed (8 Sep 2026)
- Building permit obtained
Scope of work
- Site development plan.
- Architectural and building design.
- Approvals and multi-discipline coordination.
- Building permit application filed – September 2026.
- Building permit obtained.
The project is ready to build.